FY2016
RFQ1/RFP1 SHORTLIST/SELECTION:
RFQ Issued to Firms: | 02/24/15 |
RFQ Due to MSD: | 03/18/15 |
RFP Issued: | 04/29/15 |
RFP Due to MSD: | 05/21/15 |
Selection Process Completed: | 06/19/15 |
Projects Included in RFQ1/RFP1:
1. Coldwater Creek WWTF Final Clarifiers Replacement (12504)
- Crawford Murphy & Tilly Inc.
- Donohue & Associates, Inc. — SELECTED
- Tetra Tech, Inc.
2. Comprehensive Ammonia and Nutrient Removal Master Plan (12070)
- Black & Veatch Corporation — SELECTED
- Jacobs Engineering Group, Inc.
3. Degiverville Combined Sewer Relocation (11136)
- ABNA Engineering, Inc.
- Farnsworth Group, Inc. — SELECTED
- Gonzalez Companies, LLC
4. Caulks Creek Forcemain Rehabilitation (11789)
- Engineering Design Source, Inc.
- M3 Engineering Group, PC — SELECTED
- Thouvenot, Wade & Moerchen, Inc.
RFP2 SHORTLIST/SELECTION:
Interest Statement Issued to Firms: | 02/24/15 |
Interest Statement Due to MSD: | 03/18/15 |
RFP Issued: | 05/22/15 |
RFP Due to MSD: | 06/16/15 |
Selection Process Completed: | 07/17/15 |
Projects Included in RFP2:
1. Lemay Pump Stations 1 and 2 Improvements (12488)
- Crawford Murphy & Tilly Inc.
- Donohue & Associates, Inc. — SELECTED
- Wade Trim, PC
2. Natural Bridge Rd – Darby to Chevrolet Combined Sewer Relief (12536)
- Access Engineering, LLC — SELECTED
- Cole & Associates, Inc.
- Heideman & Associates, Inc.
3. Deer Creek OMCI Stormwater Design (Contract A) (12461)
- CDG Engineers, Inc. — SELECTED
- CMV – Cochran, LLC
- EFK Moen, LLC
4. Rosewood Lane & Woodard Dr. Storm Sewer (10347)
5. Big Bend to Papin Storm Sewer Phase I (10035)
- EDM Incorporated
- Hart Engineering, LLC — SELECTED (10035)
- Oates Associates, Inc. — SELECTED (10347)
- RJN Group, Inc.
- TREKK Design Group, LLC
6. Hudson Rd. #1401 – #1405 Bank Stabilization (MCDW-120) (10020)
7. Cottage #206 Storm Improvements (10302)
- HR Green, Inc. — SELECTED (10020)
- Reitz & Jens Inc.
- Stantec Consulting Services Inc. — SELECTED (10302)
- Stock & Associates Consulting Engineers, Inc.
- Williams Creek Consulting Inc.
RFP3 SHORTLIST/SELECTION:
Interest Statement Issued to Firms: | 02/24/15 |
Interest Statement Due to MSD: | 03/18/15 |
RFP Issued: | 06/19/15 |
RFP Due to MSD: | 07/14/15 |
Selection Process Completed: | 08/14/15 |
Projects Included in RFP3:
1. General Services Agreement – Construction Management (2016) (11752)
- AFRAM Corporation — SELECTED
- Basilico Engineering Incorporated
- Shalom Services Corporpation
2. General Services Agreement – Facility & Sewer Design (2016) (11760)
- George Butler Associates, Inc.
- Horner & Shifrin Inc.
- Tetra Tech, Inc. — SELECTED
3. General Services Agreement – Survey Services (2016) Contract A (11764)
4. General Services Agreement – Survey Services (2016) Contract B (12394)
5. General Services Agreement – Survey Services (2016) Contract C (12395)
6. General Services Agreement – Survey Services (2016) Contract D (12405)
7. General Services Agreement – Survey Services (2016) Contract E (12406)
- Civil Design, Inc. — SELECTED (12405)
- Clayton Engineering Company
- Gateway Land Services, Inc.
- Hanson Professional Services inc. — SELECTED (12406)
- Juneau Associates Inc., PC
- Kuhlmann Design Group, Inc.
- Sabur, Inc. — SELECTED (11764)
- Sterling Company — SELECTED (12395)
- Volz Incorporated — SELECTED (12394)