Bennett Avenue: Upper River des Peres and River des Peres Tributaries Storage Tunnel (12441)

Overview

MSD Project Clear is planning work on Bennett Avenue in Richmond Heights. Construction is several years away. This page is where Bennett Avenue neighbors can find updates, answers to questions, and materials from community meetings. We’ll add information as it becomes available. The next update is anticipated in Summer 2027.

The Bennett site will include two projects:

  1. Upper River des Peres and River des Peres Tributaries Storage Tunnel: construction of an intake structure that sends combined sewer overflows to a deep storage tunnel. Estimated construction timeframe: intermittently from 2030 to 2033.
  2. Hampton Park Combined Sewer Relief and Creek Channelization: removal of six combined sewer overflows from Hampton Branch. Estimated construction timeframe: intermittently from 2034 to 2036. 

During construction, neighbors can expect some noise and traffic typical of an active construction site. Construction itself will take place on two properties currently in the process of being acquired by MSD Project Clear.

Current Activities

Current activities include ongoing design work, property acquisition, and historic review with the State Historic Preservation Office (SHPO).

  • Design is about 60% complete on the Tribs Tunnel work; Hampton Park is at a much earlier phase of design.
  • Two properties on Bennett Avenue have been approached for acquisition. Additional acquisitions on Bennett are considered unlikely, though this cannot be fully confirmed until closer to construction.
  • A historic review is underway. The process will evaluate impact of the project on the Bennett Avenue Historic District and consider appropriate mitigation.

Stay Informed

Join our mailing list to receive occasional updates as the project progresses. The next email update is anticipated in Summer 2027, when the projects reaches the 90% design milestone.

For questions, please contact:

Patricia Pride
MSD Project Manager
paprid@stlmsd.com
314-768-6275

Note: Please keep in mind we’re sharing information on this project earlier than usual so we don’t have all the answers yet. 

We are sharing information early, at 60% design, because a property on Bennett came up for sale and MSD Project Clear purchased it. We wanted neighbors to understand why and know what type of work to expect.

Some details won’t be known until design is finalized and others won’t be known until a construction contractor is selected around 2030 and develops detailed staging plans for construction. We are sharing what we know now and will provide updates as more is known.