Current Opportunities & Selections – FY2023

RFQ1/RFP1 SHORTLIST/SELECTION:

RFQ Issued to Firms: 02/25/22
Qualifications Due to MSD: 03/23/22
RFP Issued: 05/06/22
Proposals Due to MSD: 06/01/22
Selection Process Completed: 07/01/22

Projects Included in RFQ1/RFP1:

1. Webster Groves Trunk E Sanitary Relief (SKME-0628) (10794)

  • Farnsworth Group Inc.
  • Burns & McDonnell Engineering Company Inc.                   SELECTED
  • Stantec Consulting Services Inc.
  • Wood Environment & Infrastructure Solutions, Inc.

2. BC-01 Phase III and BC-02 Phase II Sanitary Relief (I-170 to Heatherwood Dr) (12090)

  • Crawford Murphy & Tilly Inc.
  • HR Green, Inc.
  •  Lochmueller Group, Inc.                                                             SELECTED

3. Glen Echo Sanitary Relief (Engelholm Ave to Henderson Ave) (12176)

  • Benham Design, LLC
  • Civil Design Inc.                                                                             SELECTED
  • Gonzalez Companies, LLC

4. S Brentwood Blvd Sanitary Relief (Daytona Dr to Walinca Terrace) (12195)

  • ABNA Engineering, Inc.
  • David Mason & Associates, Inc.                                                 SELECTED
  • George Butler Associates, Inc.

 

PLEASE NOTE:  Request for Proposals for these 4 Stormwater projects are expected to be issued in December, after the Missouri Department of Natural Resources issues grant awards for ARPA grant funding for our area.  

5. General Services Agreement – Stormwater Design for ARPA Grant Projects (2023) Contract A (13710)

  • EDM Incorporated
  • EFK Moen, LLC
  • Intuition & Logic Engineering, Inc.                                          SELECTED
  • M3 Engineering Group, PC

6. General Services Agreement – Stormwater Design for ARPA Grant Projects (2023) Contract B (13711 )

  • EDM Incorporated
  • EFK Moen, LLC
  • Intuition & Logic Engineering, Inc.
  • M3 Engineering Group, PC                                                        SELECTED

7. General Services Agreement – Stormwater Design for ARPA Grant Projects (2023) Contract C (13712)*CANCELLED*

8. River Des Peres Channel Rehabilitation (13577) 

  • Horner & Shifrin, Inc.
  • Jacobs Engineering Group Inc.
  • Reitz & Jens Inc.                                                                           SELECTED

RFP2 INTEREST STATEMENT:

Interest Statement Issued to Firms: 02/25/22
Interest Statement Due to MSD: 03/23/22
RFP Issued: 05/27/22
Proposals Due to MSD: 06/22/22
Selection Process Completed: 07/28/22

Projects Included in RFP2:

1. Geyer Sanitary Relief (W. Monroe Ave to W. Essex Ave) (12174)

2. Lindsay Lane Sanitary Relief (Lindsay Lane to Lindbergh Blvd) (13629)

  • Cole & Associates, Inc.
  • Hanson Professional Services, Inc.                    SELECTED (12174)
  • Kuhlmann Design Group, Inc.
  • RJN Group, Inc.                                                     SELECTED (13629)

3. Grand Glaize WWTF Grand Glaize Creek Bank Stabilization (13630)

  • Engineering Design Source, Inc
  • Geosyntec Consultants, Inc
  • Intuition & Logic Engineering, Inc                     SELECTED

4. Grand Glaize WWTF Repairs and Improvements (2023) (13221)

  • CDM Smith Inc
  • GHD Inc                                                                   SELECTED
  • Horner & Shifnn, Inc

5. Gravois Creek OMCI Stormwater Design (2023) (13714)

  • Hart Engineering, LLC
  • Oates Associates, Inc                                             SELECTED
  • Tepa Engineering Services, LLC