White Plains Sanitary Relief (12280)

White Plains Sanitary Relief (12280)

As part of a long-term effort to reduce basement backups and sewer overflows, MSD[3] Project Clear[1] is constructing a project to replace approximately 2,835 feet of undersized wastewater sewers. In addition, this project will reduce creek bank erosion and improve water flow by stabilizing 852 feet of natural creek in the City of Chesterfield.

About the Project

Public Meeting - June 1, 2023

Project Map

What is the goal of this project?

MSD Project Clear is investing approximately $1.5 million to improve the wastewater sewers and prevent creek bank erosion in the City of Chesterfield. The goals are to reduce basement backups and sewer overflows, which occur when the sewers become overloaded during intense rainfall, and prevent creek bank erosion by installing rock stabilization to protect some of the nearby private properties from creek erosion.

Project Facts

  • Construction is estimated to begin in Spring 2023.
  • MSD Project Clear will replace approximately 2,835 feet of wastewater pipe.
  • The pipe size will increase to between 8 and 15-inches in diameter, allowing a larger amount of wastewater to flow through the system.
  • MSD Project Clear will also install approximately 852 feet of natural channel stabilization.

What can residents expect?

This project will be constructed by digging through the surface of the ground in a process known as “open-cut” construction. The pictures above depict what a neighborhood will look like before, during and after a typical open-cut project. In the segments crossing Still House Creek Road, the contractor will use tunneling to avoid major traffic implications. With any type of construction, residents can expect to see and hear heavy equipment during the sewer excavation process.

Traffic and Access: As much of the construction will take place in unpaved areas, MSD anticipates minimal traffic disruptions. Drivers may experience temporary lane closures as construction crosses roadways and will see increased construction traffic. Traffic control will be provided as needed.

The contractor will follow all local ordinances and will notify all properties of any temporary access restrictions. As the majority of construction will take place in backyards, MSD anticipates minimal property access restrictions. The contractor will give all property owners ample notification prior to any access restrictions.

Restoration: After all new sewer pipes are installed, the contractor will restore the construction site according to all MSD and local requirements. This could include sodding any disturbed areas, replacing disturbed pavement, reinstalling fences, etc.

At least one MSD Inspector will be on-site part of the day for every day the contractor is working.

What is the timeline?

This is the current tentative project schedule. This is subject to change based on a variety of factors including weather.

  • Estimated construction start: Spring 2023
  • Estimated project duration: Approximately 9-12 months

FAQs

While MSD’s contractor is connecting a home’s lateral to the new wastewater sewer, they may ask residents to limit water use. In general, this process can take between two to five hours, depending on the complexity of the connection. The contractor will notify property owners in advance.

MSD does not anticipate other utility services being disrupted during this project. We will work with Missouri One Call to locate utilities before beginning construction. Occasionally, the contractor may run into utilities that were not located by Missouri One Call which could result in temporary utility disruptions. If this happens, MSD will work with the utility to restore service as quickly as possible.

Trees may need to be removed to construct parts of this project. If there are good options to avoid removing trees, MSD will make every attempt to do that. Property owners with trees that will need to be removed that are not located in already existing easements will have been compensated for the removal through the easement acquisition process.

In general, District policy is to restore affected areas to the same or better conditions than before the project. Streets that are disturbed through this project will be replaced and repaved with similar material. The project’s restoration will meet all local and District requirements.

During easement acquisition, an MSD Right of Way Agent will work with property owners to discuss restoration on their property. Most yard areas will be resodded with the same material. Driveways, walkways, and other hard surfaces will be restored using the same materials that are currently in place. In wooded ground areas, District[2] policy is to seed the disturbed areas.

During active construction, some property owners may experience driveway access restrictions for a short period of time. The contractor will notify property owners in advance of any temporary access restrictions to allow them time to move their vehicles. The contractor will also fill trenches with gravel or place steel plates over trenches during non-working hours so residents can use their driveways during those times

MSD will instruct its contractor to keep the site reasonably clean and clear of debris. MSD will have an inspector on site every day during active construction. Prior to the start of construction, MSD will give every resident and property owner along the construction site the inspector’s contact information. Community members are encouraged to bring any concerns to the on-site inspector or any other member of the project team.

FAQs section will be updated as questions are sent in to the Project Manager.

Previous Public Meeting - May 12, 2022

Terms defenitions
1. Project Clear. MSD Project Clear is a long-term initiative to improve water quality and alleviate many wastewater concerns in the St. Louis region.  It will invest billions of dollars over a generation in planning, designing, and building community rainscaping, system improvements, and through an ambitious program of maintenance and repair.
2. District. Refers to The Metropolitan St. Louis Sewer District or MSD. The District is organized pursuant to Article VI, Section 30 of the Missouri State Constitution that empowers the people in the City of St. Louis and St. Louis County “to establish a metropolitan district for functional administration of services common to the area.”
3. MSD. Metropolitan St. Louis Sewer District